19I266511 Implement LDAP to Office 365

0 %

Status

Project is 0 % complete, starting on Mon 2/18/19 and ending on Tue 12/31/19.

On Hold [On Hold]

0% complete, updated on Fri 9/6/19 11:13 AM by Arturo de los Santos

Changed status from New to On Hold.
Changed health from None - No health has been set to On Hold.

Details

Dates
Mon 2/18/19 - Tue 12/31/19
Acct/Dept
Information Technology Services
Type
General / ITS Departmental Projects
Health
On Hold
Classification
Level 2 Project
Created
Wed 8/3/16 8:17 AM
Modified
Fri 9/6/19 11:13 AM

Description

The original start date on this project was September of 2016 with an expected end date of July 2018. Since no progress had been made on this the project was canceled. It will now be reopened as there is a need to move forward with this.

Goals

  1. Build on Trinity University Strengths

Risks

  1. Low Complexity

  2. Low Institutional Impact

  3. Low ITS Security

  4. Medium Resources

  5. Low Schedule

  6. Low Technology

Manager(s)

Stakeholders (1)

Fred Zapata

Fred Zapata

Senior Director ITS - PMO
Informed
CITO
Thu 9/1/16 4:53 PM